During this exciting season of renovation, this page will hold all of our most recent updates for you to more easily access. It is our desire as a church to keep you as up-to-date as possible, so we will continue to add pictures and progress reports to this page. Please check back frequently and let us know if you have any questions by sending us an email here. We'll do our best to contact you as soon as possible!

  • Sanctuary Renovation Update - 11/21/22

    We are in the building!!  The inspection has passed with some minor items to fix. The dedication ceremony and celebration was a success and a real gift from the Lord. Thank you to EVERYONE who made this move possible!


    -The pews arrived, were assembled, and installed this week!  (pictured above)
    -HouseRight conducted their training for the AVL system.
    -Altar and AVL tables were completed and installed.

  • Sanctuary Renovation Update - 11/17/22

    Home stretch!  Only a few days until the dedication!!!


    -Interior Doors installed in the sanctuary
    -Sacristy cabinetry completed
    -Hand rail installed at the stage
    -Flooring completed in the sanctuary
    -Painting completed


  • Sanctuary Renovation Update - 11/7/22

    The work has continued on schedule this week!  We are nearer to completion!
    -Exterior siding and paint is pictured above!
    -HouseRight completed their work installing our new audio and visual system.
    -Flooring underway in sanctuary
    -Painting occurred throughout the hallways
    -Sconces replaced in hallways

  • Sanctuary Renovation Update - 10/28/22

    The work on the renovation project continues as scheduled!  Praise be to God!

    -The sanctuary cross went up this week!  
    -The tile in the Narthex bathrooms was finished.
    -Trim work continuing on the windows.
    -Flooring underlayment completed in the sanctuary and narthex.
    -Door installation began.

  • Sanctuary Renovation Update - 10/21/22

    The Windows Have Been INSTALLED!!!  The long-awaited windows were installed this week!  Thank you for your prayers!  Now the renovation project can really pick up speed to reach the finish line in the coming weeks!  We are so excited! (Pictured: one very happy senior warden, worship director, and rector!!)


    This Week's Building Update:
    -Prime contractor installed floor underlayment as prep for the luxury vinyl tile in the sanctuary and narthex
    -Jerusalem cross is now installed in the narthex
    -Pendant lights hung
    -Prime contractor completed installation of new tile in the Narthex restrooms